Every posting cites its governing paragraph. A position and a citation, not accounting advice.
TokenCapEx
Prepaid assetReserved GPU commitment

Reserved GPU commitment

The posting

A multi-year reserved GPU commitment is a signed commitment, not consumption. Where the contract is a service contract rather than a lease, the amount paid in advance is a prepaid asset, not an expense and not a capitalized intangible on day one. It unwinds as capacity is drawn down: to cost of revenue when it serves a paid product, to expense for experimentation, or to a software asset for capacity used in an internal-use build ASU 2018-15.

Commitment vs consumption

The mistake is treating the whole committed amount as the period's OpEx. A reserved commitment gives you the right to future capacity; you have consumed nothing at signing. Book the advance payment as prepaid compute and release it as you actually draw down the reserved capacity. The commitment-vs-consumption axis is the single most important read on this instrument.

Prepaid assetIllustrative example, not client data
CapEx / Balance sheet
OpEx / P&L
DrPrepaid compute (asset)X
CrCashX
At signing: the committed advance is set up as a prepaid asset. Figures illustrative.

First, check whether the contract contains a lease

The prepaid posting assumes a service contract. ASC 842 defines a lease as "a contract, or part of a contract, that conveys the right to control the use of identified property, plant, or equipment (an identified asset) for a period of time in exchange for consideration." Capacity drawn from a provider's shared fleet, where the provider has a substantive right to substitute the hardware, does not give you an identified asset. Dedicated servers or a named cluster that only you use and direct may: test whether you get substantially all the economic benefits of that hardware and the right to direct its use. If the contract contains a lease, the lease component is booked as a right-of-use asset and a lease liability, not as prepaid compute. Under IFRS the equivalent test is in IFRS 16 Leases.

Where the drawn-down capacity lands

Term length drives the schedule

The commitment term sets the maximum period over which the prepaid unwinds: a three-year commitment unwinds over at most three years. Software built with the drawn-down capacity is a separate asset, amortized over its own useful life.

Prepaid unwinds across the committed term
Y1
Y2
Y3

Questions this posts answers

Is a reserved GPU commitment CapEx or OpEx?
Neither at signing. As a service contract, the amount paid ahead is a prepaid asset that unwinds as capacity is consumed, landing in COGS, expense or a capitalized asset depending on what the capacity is used for. If the contract gives you control of identified, dedicated hardware it may contain a lease under ASC 842, booked as a right-of-use asset and lease liability.
Does a reserved GPU commitment contain a lease under ASC 842?
Only if it conveys the right to control the use of identified hardware for a period of time. Capacity on a shared fleet the provider can swap out has no identified asset; dedicated servers you alone use and direct may contain a lease, booked as a right-of-use asset and a lease liability.

Posts to

Primary sources

Ledger current as of 2026-10-23. A position and a citation, not accounting advice. See how we cite.